Short answer: Yes, on many Burlington lots. The City allows up to three ARUs, including a detached one. You start with a Pre-Building Approval application, then apply for the building permit, which the City says it issues within ten business days once complete. ARU zoning and building permit fees are currently waived (City of Burlington).

Key takeaways

QuestionShort answerSource
How many ARUsOne, two or three, inside, attached or detachedCity of Burlington
First stepPre-Building Approval (zoning, engineering, forestry pre-screen)City of Burlington
PBA timingAbout 3–4 weeks with exterior work; up to 4–6 weeks at current volumesSteps guide; PBA page
Permit timingIssued within 10 business days once completeCity of Burlington
FeesARU zoning and building permit fees currently waivedCity of Burlington
Parking2 for the house; 0 for the first ARU; 1 for a second or thirdCity of Burlington

What Burlington allows

Burlington defines ARUs as self-contained units with their own kitchen, bathroom and sleeping areas, on the same property as a detached, semi-detached or townhouse dwelling. They can be inside or attached to the house, or in a separate accessory building such as a detached garage or coach house (City of Burlington). The City's ARU look-up tool shows which detached ARU types may be permitted on your property, with zoning staff confirmation required.

Permit steps

  1. Check the lot. You must be the registered owner to apply. Use the look-up tool and zoning map, or start with our free feasibility check.
  2. Pre-Building Approval. Submit drawings (especially for exterior work or modular units), a tree permit if trees come out, and a grading and drainage certificate. Staff check completeness within about six business days, then coordinate Zoning, Engineering and Forestry review: about three to four weeks with exterior work per the steps guide, or up to 4–6 weeks at current volumes per the Pre-Building Approval page.
  3. Building permit. For an ARU in an accessory building you may apply before the Zoning Clearance Certificate is issued (since January 1, 2025); the permit is issued after the Grading and Drainage Certificate, and construction starts once any Tree Permit is issued. Submit the building permit application. The City screens it within two business days and issues within ten business days once complete.
  4. Build and inspect. Start within six months or the permit expires. The City schedules inspections within two business days and issues an Occupancy Permit at the end.

Source: City of Burlington — Steps to build an ARU.

Fees and parking

The City says ARU zoning and building permit fees are currently waived; confirm at pre-screening. Parking is two spaces for the main home, none for the first ARU and one for a second or third ARU (City of Burlington).

Local context: garden suites in Burlington.

Related permit guides: Oakville · Milton · Hamilton.

To compare Burlington with other cities, see the GTA garden and laneway suite rules comparison.

FAQs

Often, yes. Burlington allows one, two or three additional residential units (ARUs) on a property with a detached, semi-detached or townhouse dwelling, including in a separate accessory building. Not all properties can fit one.